Metro

Lagos Spends N339m On Magazines, Only N33m On Ibeju-Lekki Electricity

The Lagos State Government spent N382.81m on magazines and periodicals, newspapers and telephone charges, alongside N10.04bn on plant and generator fuel between January and September 2026, amid persistent electricity challenges in more than 40 communities in Ibeju-Lekki Local Government Area and Lekki Local Council Development Area of the state.

The expenditure was contained in the Lagos State Budget Implementation Report for the third quarter of 2026, under the Ministry of Energy and Mineral Resources.

A breakdown of the report showed that the government spent N339m on magazines and periodicals, N43.43m on telephone charges and N380,000 on newspapers during the first nine months of the year.

The N339m spent on magazines and periodicals represented 66 per cent of the N513.36m budgeted for the expenditure in 2026.

Similarly, the N43.43m spent on telephone charges represented 33.2 per cent of the N130.73m budgeted for the year, while the N380,000 spent on newspapers accounted for 1.5 per cent of the N24.76m allocation.

The report further showed that the state government spent N10.04bn on plant and generator fuel during the nine-month period, representing 48 per cent of the N20.93bn budgeted for the expenditure in 2026.

Of the amount, N1.78bn was spent in the third quarter alone.

The combined expenditure on generator fuel, magazines and periodicals, newspapers and telephone charges stood at N10.42bn between January and September 2026.

The expenditure came as residents of more than 40 communities in Ibeju-Lekki continued to complain about prolonged electricity shortages, which they said had persisted for about 15 years.

In a report published by Lagos Reporters in September 2026, the residents said the prolonged blackout had disrupted education, healthcare and commercial activities in their communities.

The affected communities include Akodo, Magbon Alade, Alasia, Orimedu, Eleko, Osa-Oroko, Ise, Solu, Tiye, Mobido, Idasho, Ilege, Magbon-Segun, Idotun, Itokin, Lekuru, Okunraiye, Oshoroko, Shiriwon, Ibekodo, Itamarun, Oniyanrin, Otoolu, Folu, Ikegun, Lepia, Okun-Ise, Okun Abumiti, Igbogun, Idata, Obada and Ogogoro, among others.

The residents lamented that children were forced to study with candles and kerosene lamps, while hospitals struggled to preserve vaccines and provide adequate services at night.

Small businesses, including welding workshops, barbing salons, cold rooms and tailoring businesses, were also said to have suffered losses due to the absence of reliable electricity.

The residents expressed frustration that their communities continued to experience prolonged power outages despite hosting major economic investments, including the Dangote Refinery, Lekki Deep Sea Port and Lekki Free Trade Zone.

They questioned why communities hosting some of the state’s largest industrial projects remained without reliable electricity, while the facilities operated continuously.

The residents further argued that the situation was particularly troubling given the more than N2.6tn in revenue they said Lagos State had generated.

In November 2022, the Lagos State Government announced a partnership with the African Development Bank, United States Agency for International Development and National Rural Electric Cooperative to improve electricity supply to communities in Ibeju-Lekki.

According to the residents, they cooperated with the process following appeals from traditional rulers and local council chairmen but had yet to experience meaningful improvements several years later.

They are demanding the restoration of electricity to affected communities, the installation of injection substations and new transformers, and repairs to damaged cables along the Eleko-Akodo axis.

They also called for transparency regarding the proposed AfDB and Lagos State electricity project.

Meanwhile, the budget implementation report showed that the government allocated N832.43m to the electrification of Ibeju-Lekki in 2026.

However, only N33.69m had been spent on the project between January and September, representing 4 per cent of the annual allocation.

The report indicated that no expenditure was recorded under the project in the third quarter, while N798.74m remained unspent as of September 2026.